Alternative fuel system for Kiln Riser Duct firing at CRH Slovakia

 

In 2017 A TEC and CRH Slovakia have installed an alternative fuel system for kiln riser duct firing in Turna Nad Bodvou, Slovakia. The Turna Nad Bodvou cement plant has already operated a SAF system for the main burner which consists mainly of a double truck docking station and a dosing system.

The riser duct itself has a gas residence time of approx. 3 sec, so up to 25 % TSR at the riser duct are possible by limitation of the material to max. 50 mm (2D) size. The SAF is now injected above the bypass take-off point (in the location of the current meal inlet). To limit the CO emissions, a hot ignition zone has been created at the SAF injection. This was realized by moving the existing meal inlets to the riser duct of about 8 – 10 m.

As the kiln is equipped with an extended kiln riser duct (without tertiary air) it is possible to fire a significant amount of fuel in this kiln riser duct. Now about 20 % of the total fuel as SAF with main burner quality can be fired.

About A TEC

A TEC Production & Service GmbH is an engineering and technologies company located in Austria. It is focused on optimization and efficiency improvement of cement plants. In total, A TEC has successfully completed more than 600 cement plant optimization projects.

Part of modern cement plant operation is the usage of alternative fuels. A TEC can offer the complete AF system for nearly any kind of solid and liquid waste materials including material handling, preparation, storage and feeding into the kiln.