Ivanhoe Mines announced its financial results for the year ended December 31, 2010.
The approved 2011 capital budget for Oyu Tolgoi is estimated at $2.3 billion. Principal components of the 2011 construction program include $561 million for the 100,000-tonne-per-day concentrator complex; $186 million for the initial mining fleet and to start pre-stripping of the Southern Oyu open-pit mine; and $713 million for project infrastructure, electrical power and completion of the process-water supply.
The number of workers assigned to the Oyu Tolgoi site recently surpassed 7,000 for the first time. On-site jobs at Oyu Tolgoi are expected to peak at almost 14,000 in mid-2011, with an additional 3,700 Mongolians receiving skills training sponsored by Oyu Tolgoi.