Ivanhoe Mines announces financial results and review of operations for the third quarter of 2011
Overall construction at Oyu Tolgoi continues to advance on budget and reached a 54.4% level of completion at the end of Q3'11. Key elements of the project, including the concentrator complex, primary crusher and tailings-thickening ponds, remain ahead of schedule. Total capital invested in the project to the end of Q3'11 was approximately $3.2 billion. Facilities required for first ore production in mid-2012 remain on schedule and commercial production is expected to commence in the first half of 2013.