G Mining declares commercial production at Tocantinzinho gold mine in Brazil

Construction of the Tocantinzinho mine. Credit: G Mining Ventures

G Mining Ventures (TSX: GMIN) has officially become Brazil’s newest gold producer after declaring commercial production at its Tocantinzinho mine in Para state on time and on budget in less than two years of construction.

The milestone was achieved following 30 consecutive days of operations, during which the mill operated at a minimum of 60% of nameplate throughput. During August, it ramped up to 76%, processing more than 300,000 tonnes at a recovery rate of 88%.

“This achievement is the culmination of 5.8 million person-hours focused on building, testing and ramping up production at Brazil’s newest major gold mine,” G Mining CEO Louis-Pierre Gignac said in a press release on Tuesday.

Last month, the Canadian miner received Tocantinzinho’s operating licence and sold its first gold produced to a refinery in Switzerland. First pour and hot commissioning were achieved earlier in the summer.

G Mining will now focus on ramping up mine operations through 2024, testing the processing circuits’ ability to handle nameplate loads while improving recovery to 90%. The company is targeting its nameplate throughput of 4.7 million tonnes per annum by early 2025.

Tocantinzinho is engineered to have a 10.5-year mine life with an average annual gold production of 174,700 oz., including 196,200 oz. for the first five full years.

Comments

Your email address will not be published. Required fields are marked *