Posts by Endomines:

Test Runs of the Process Plant Expansion Have Commenced at Pampalo – Capacity Increase Possible with Current Permit

Endomines has completed the installation of the new processing equipment of the processing plant and commenced the test runs for the increased capacity at its Pampalo Gold Mine Processing plant. The second grinding mill and increased flotation capacity will increase plant processing throughput to 45-50 tonnes/hour (annualized 380 000 tpa) before the end of February 2013.