Lucara Diamond Corp.: development of AK6 diamond mine passes half way point and remains on time and within budget
Lucara Diamond provided an update on the development of its 100% owned AK6 diamond project in Botswana. The AK6 mine, to be commissioned by year end, will ramp up to full production in early 2012 to deliver over 400,000 carats of high quality diamonds in its first year of operation.
As at the end of May there were over 400 construction crew members on site and a total of 326,000 hours worked. With the overall project execution at 64% the project remains on target for process plant commissioning to commence in the Q4 of this year. Engineering is now 91% complete; procurement is at 81%; fabrication and delivery at 55%; and construction at 39% complete.